Saturday, January 29, 2011

Tiles






The tiling has started. The tiles got delivered on Thursday and the screeting was completed on Friday. The tiles wil be done on Wednesday and carpet will start on Thursday. Trying to organise splashback, driveway and fence.
Here is some pics of the tiles and kitchen.

Tuesday, January 25, 2011

pci today and handover
















Met ss today, we walked through the house pointing out defaults. Most things looked good, just some paint touch ups. They forgot to do the skylight and the mirror robe sliding doors aren’t in.
The bank stuffed us around a little and wasn’t releasing the funds. We got a call from Allworth at 4:30 saying the funds had gone through. We drove straight there and picked up the keys at 4:59.
The tiles are booked in for this Friday and carpet next Wednesday. We will move in and hopefully do driveway, fence and splashback straight after we move in.
Here is a few pics...

Thursday, January 20, 2011

Practical Completion Inspection set!

Got a call from ss informing us that pci will take place next week. Not sure if they are going to finish on time, as they only delivered the toilets today. Hopefully they will get a move on. Still to be completed is the pluming, appliances, electrical, skylight, clean up. Was wondering if anyone knew how long after pci that you receive keys?

Tuesday, January 18, 2011

Painting finished & bagged and painted :)




Garage door was installed yesterday and painting has finished today. They bagged and painted the bottom half of the front and finished of the eves and meter box. Plumping should take place on Thursday and the electrical fit out on Friday. Next week will hopefully just be bits and pieces and clean up. So still looking good to get keys beginning of February.

Monday, January 10, 2011

Painting has started!



It looks like Allworth are back from their Christmas break. Drove past today and saw that paiting has started. Called my ss and he is confident that we will have the keys by the 31st of Jan. We are very pleased with this time frame. However, their 15week build does not finish till 3rd of March. So they have time incase something gets delayed...
After we get the keys we plan to tile and carpet, then move in and organise fence and driveway. :)